How long does the TOP have to provide a copy of the voltage schedule to the RC or neighboring TOPs upon request?

Prepare for the NERC Reliability Coordinator Exam with in-depth study materials including flashcards and multiple choice questions. Each question provides insights and explanations to enhance your learning. Become confident in your test-taking skills!

The correct answer is based on established timelines for communication between Transmission Operators (TOP) and Reliability Coordinators (RC) or neighboring TOPs. According to the guidelines, when a request is made for a copy of the voltage schedule, the TOP is required to respond within a timeframe that allows for effective operational planning and coordination.

In this case, the stipulated timeframe is 30 calendar days. This duration ensures that there is enough time for the TOP to compile the necessary data and share it, ultimately facilitating better reliability and operational awareness among interconnected systems. This process is crucial because voltage schedules play a significant role in maintaining grid stability, and timely sharing of this information helps all participating entities to align their operations more effectively.

The specific choice of 30 days highlights the need for prompt communication while providing an adequate window for various operational and logistical considerations on the part of the TOP.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy