How often should TOP review and submit the restoration plan to RC?

Prepare for the NERC Reliability Coordinator Exam with in-depth study materials including flashcards and multiple choice questions. Each question provides insights and explanations to enhance your learning. Become confident in your test-taking skills!

The requirement for the Transmission Operator (TOP) to review and submit the restoration plan to the Reliability Coordinator (RC) on an annual basis is essential for maintaining effective operational readiness and ensuring reliability during outages or emergencies. An annual review allows the TOP to assess any changes in system configuration, operational practices, or regulatory requirements that could impact the restoration plan's effectiveness.

This regular review cycle ensures that the plan remains relevant and incorporates the latest data, technology advancements, and lessons learned from past incidents or drills. By adhering to this 12-month framework, the TOP can work collaboratively with the RC to ensure that all protocols are up-to-date, thus promoting a more coordinated response in the event of a system disturbance.

The other intervals suggested, such as every 6 months or every 2 years, may not provide the regular oversight needed to adapt to ongoing changes in the system. Additionally, scheduling reviews on an as-needed basis may lead to gaps in readiness, as it may not account for routine updates required due to evolving industry standards or unexpected incidents. Thus, the annual submission requirement strikes a balanced approach to operational preparedness.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy