Which entity is required to submit a report to the RC following the termination or downgrading of EEA3?

Prepare for the NERC Reliability Coordinator Exam with in-depth study materials including flashcards and multiple choice questions. Each question provides insights and explanations to enhance your learning. Become confident in your test-taking skills!

The entity required to submit a report to the Reliability Coordinator (RC) following the termination or downgrading of an Energy Emergency Alert Level 3 (EEA3) is the Energy Dispatched Entity (EDE). This requirement is critical because it ensures that the RC is kept informed about significant operational changes during energy emergencies. EEA3 indicates a dire situation where load-shedding or other emergency measures are in effect.

The EDE plays a crucial role in managing resources and responding to the needs during such alerts, making it essential that they communicate the status of the emergency accurately and promptly once it has been terminated or downgraded. This communication helps maintain coordination and restore normal operations effectively, as it provides the RC with up-to-date information regarding the stability and reliability of the bulk power system.

Other entities, such as Transmission Operators (TOP), Generator Owners and Operators (GOP), and Balancing Authorities (BA), have their own responsibilities during an EEA3 but are not the specific entities tasked with reporting the termination or downgrading of the alert. Each entity has its role within the system, ensuring that operations can recover from emergency situations in a coordinated manner.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy